Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Evaluate the expression when a = 3 and b = 5. 7a – 3b + 2 A. 7 B. 15 C. 8 D. 4
The auditory cortex is located in which lobe of the brain?
Holly would like to run an annual major disaster recovery test that is as thorough and realistic as possible. she also wants to ensure that there is no disrupti
Research has shown that neurogenesis in adult rats can be enhanced by:
In a simple regression model y = ß0 + ß1x + ε, ß1 represents the ________.
Systems of taxonomy have been established according to the notion of::
The number m and 58 are additive inverses. Drag and drop 58 and m to their correct positions on the number line.
find the slope that goes through 10, 6 and 1, 5
In 1999, sean fanning, john fanning, and sean parker invented napster, a global, free-of-charge, peer-to-peer music sharing program. prior to napster, no such p
Solve the equation: 0.25r - 0.125 + 0.5r =0.5 +r Show all work plz