It takes 5 men 12 days ro complete a job how many days does it take 3 men to complete the job

Respuesta :

eloo59980
eloo59980 eloo59980
  • 04-01-2021

Answer:

5=12

3=? then Criss cross it and you will get 12*3 divided by 5 then you get 7.2

so the answer will be 7 days

Answer Link

Otras preguntas

You spot a small bird with bright yellow feathers on your back porch. Which one of the following books might be a good place to find out what kind of bird you'
How many valence electrons does a carbon atom have?
What was the music in 1776?
When and where was Edgar Allan Poe born
Triangle DEF is reflected over the y-axis, and then translated down 4 units and right 3 units. Which congruency statement describes the figures? ΔDEF ≅ ΔSUR ΔD
Mary has saved 17.50 in the past three weeks at this rate how much will she save in 15 weeks
what does henry david thoreau believe a person
How do you say, "Her nationality is Portuguese?" In Spanish
Which characteristic does an object with a constant acceleration always have?
does a point have width